Shepherds Bush Station

A new station was constructed at Shepherd’s Bush on Network Rail’s West London Line in association with the £550m White City Development.

The new station is located just north of the Holland Park roundabout in west London and comprises two four car platforms connected via a footbridge and lifts. The new station concourse and ticket office are adjacent to the existing Shepherd’s Bush Underground Station on the Central Line which Waterman also worked on.

One of the biggest challenges of the project was working with 24 hours/7days a week rail traffic. This dictated the form of the structures and foundations to allow construction without the use of heavy plant adjacent to the railway. Other constraints included existing signals that could not be disturbed, communication cables and 25,000 volt power cables along the line of the platforms.

The approved design for the platforms involved them being built to the side and slid towards the rails. Later negotiations with Network Rail enabled the use of fully finished pre-cast platforms and retaining walls, fabricated in Germany and craned into position in short possession periods. The off-site construction of the units allows for a higher quality finish and decreases the time spent on site for installation.

This was the first use of this system in Britain but has already been adopted elsewhere.

Waterman was responsible for the civil and structural design throughout the development and construction phases. Waterman also provided the M & E tender design information.

Related Projects

  • Clongriffin Railway Station

    This new suburban rail station at Clongriffin aimed to serve large residential communities on the North fringe of Dublin.

  • Quadrant:MK

    As part of a national business improvement plan Network Rail commissioned a new 410,000ft2 office building in Milton Keynes for up to 3000 staff.

  • Walker Construction

    We have been working closely with Walker Construction (UK) Ltd delivering a number of bespoke rail improvement schemes.

  • South West Trains

    Stagecoach South Western Trains Ltd have undertaken major upgrades at stations across their network.

You Might Also Like…

  • Will the National Infrastructure Commission unlock our potential? 5 October 2015

    The National Infrastructure Commission (NIC) announced at the Conservative party conference will be headed by Labour peer Lord Adonis and has its work cut out.

  • Waterman lands four year framework 2 June 2015

    Waterman Group is delighted to announce the appointment of the Merseytravel Consultancy Services Framework.

  • TBM Arrival at Woolwich Station Box 6 June 2013

    Following the completion of the below ground Station Box structure and hand over to Crossrail ahead of the programme in February/March 2013, a significant milestone was achieved by arrival of the Tunnel Boring Machine (TBM), named Sophia on 21st May 2013.