RIBA Stage 0: Strategic Definition
Principal Designer Activities
- Review the project brief and strategic objectives and incorporate into PCI.
- Identify significant health and safety considerations that may influence project viability.
- Advise the Client on their duties under CDM 2015.
- Consider site-specific constraints and existing hazards.
Output
- Initial CDM Client Duty Advice.
- High-level risk review.
- Advice on duty holder appointments and/or procurement route.
RIBA Stage 1: Preparation and Briefing
Principal Designer Activities
- Assist the Client in defining project requirements, aims and objectives relating to safety.
- Gather existing health and safety information.
- Identify significant project risks.
- Establish arrangements for design risk management and review by the design team.
Output
- Pre-Construction Information (PCI).
- Initial Project Risk Register.
- Design Risk Analysis/Assessment from the Design Team.
RIBA Stage 2: Concept Design
Principal Designer Activities
- Attend design team meetings (observe coordination and risk management).
- Challenge risk through design principles.
- Coordinate health and safety input across the design team.
- Ensure significant hazards are identified and addressed.
Output
- Meeting Attendance and/or review of minutes.
- Design Risk Review Workshops (on larger schemes).
RIBA Stage 3: Spatial Coordination
Principal Designer Activities
- Review developing design information and drawings.
- Monitor the effectiveness of design risk management.
- Ensure residual risks are clearly identified and assigned an owner.
- Manage the DRR with the design team.
- Provide CDM Advice when required.
Outputs
- Updated Design Risk Register.
- Residual Risk Information.
RIBA Stage 4: Technical Design
Principal Designer Activities
- Review drawings.
- Coordinate final design risk register to include in PCI.
- Ensure health and safety information is communicated to those involved in construction.
- Prepare information for construction phase planning.
- Ensure a Change Management process is in place to consider CDM.
Typical Outputs
- Final Design Risk Register.
- Pre-Construction Information.
RIBA Stage 5: Manufacturing and Construction
Principal Designer Activities
- Support the Client.
- Liaise with the Principal Contractor.
- Respond to design changes and associated risks.
- Review temporary works arrangements and design change implications where applicable.
- Continue coordination of design-related health and safety matters.
Output
- Design Change Comments.
- Updated Risk Register.
- Ongoing CDM Advice.
RIBA Stage 6: Handover
Principal Designer Activities
- Monitor coordinate of health and safety information required for handover.
- Monitor compilation of the Health and Safety File.
- Review completeness of information.
Typical Outputs
- Health and Safety File Review.
RIBA Stage 7: Use
Principal Designer Activities
- Support clarification of Health and Safety File information if required.
- Provide advice relating to future maintenance, alteration and demolition considerations.
Outputs
- Additional information from the design team regarding access and maintenance
- Client Support (if commissioned).
In summary, key Principal Designer deliverables throughout a project include:
- Client CDM Duty Advice
- Design Risk Register
- Design Risk Reviews
- Attendance at DTMs
- Pre-Construction Information
- Design Coordination Records/Minutes
- Residual Risk Information
- Health and Safety File Comments